Project: Proposed Rehabilitation of Toilets & Showers
Location: Seminario Mayor de San Carlos, Mabolo, Cebu City
Owner: Archdiocese of Cebu

A. Plumbing Works (Re-piping) Roughing -in Materials Labor Subtotal
Common Toilets and Showers at East Wing 156,482.00 51,600.00  
Individual Lavatories at East Wing Dormitory 279,703.00 50,400.00  
Common Toilets and Showers at West Wing 153,102.00 49,200.00  
Individual Lavatories at West Wing Dormitory 260,743.00 49,200.00  
Femail Toilet at Ground Floor East Wing 25,758.00 14,600.00  
  875,788.00 215,000.00 1,090,788.00


B. Toilet Fixtures Roughing -in Materials Labor Subtotal
Water closets (21 sets @ 5,000.00) 105,000.00    
Shower (22 sets @ 2,750.00) 60,500.00    
Lavatories (85 sets @ 2,500.00) 212,500.00    
Floor drain (22 sets @ 250.00) 5,500.00    
Area F. drains (22 sets @ 250.00) 5,500.00    
Hose bib faucets (12 pcs @ 150.00) 1,800.00   390,800.00


C. Tileworks Roughing -in Materials Labor Subtotal
300x300 Ceramic floor tiles (997 pcs @50.00) 49,850.00 16,450.50  
300x300 Ceramic wall tiles (2,589 pcs @ 50.00) 129,450.00 42,718.50  
Portland cement (95 bags @ 190.00) 18,050.00    
ABC Grouting cement (10 bags @ 112.00) 1,120.00    
  198,470.00 59,169.00 257,639.00


D. Waterproofing Roughing -in Materials Labor Subtotal
Membrane waterproofing (126 m2 @ 740.00) 93,240.00   93,240.00


TOTAL COST 1,832,467.00
ADD: 10% Contingencies 183,246.70
Preparation of plans/drawing ( 4 sheets @ 1,500.00) 6,000.00


OVERALL TOTAL COST OF CONSTRUCTION Php 2,021,713.00